Project Overview

This project includes the design and construction of a new County Administration office building to consolidate most county government departments and services into one central location. The project includes the demolition of the County Services Plaza building, to be replaced with a 113,295 square-foot four-story building.

This building will consolidate all county employees from multiple locations, including the County Services Plaza, Courthouse Annex, Albright Building, 131 Main Street, 30 Duke Street and the Circuit Courthouse.

Financial Impact

As of the fiscal year 2022 Capital Improvement Plan, the total projected cost is approximately $35.7 million. The major source of funding is general obligation bonds.

Timeline

The following time estimates are dependent upon weather and other factors, and may be subject to change.

Design

  • Design began January 2021
  • Permits expected early 2022

Demolition of County Services Plaza

  • Began in August 2021
  • Completion expected late fall 2021

Construction of new County Administration Building

  • Begin in spring 2022
  • Completion expected spring 2024

Move-in estimated for late spring 2024

Project Update

CAB 1CAB building from above

Sept. 30, 2021: Demolition Underway on County Services Plaza